Michael S. Currier Center Construction Update
July 18th
![]() |
||
| As the exterior work continues, the interior is taking shape. Light gauge stud walls are going up. Electrical, plumbing, telephone, air circulation and other systems are being installed. And the first bit of finish work, the windowsills, has begun. Here's a look down the hallway between the dance studio and rest rooms, toward the auditorium. The squatty black fixtures are the furnaces for the heating system. Currently, you can see the soon-to-be-former music wing from the floor of the dance studio. The red motor is the diesel engine that powers the sprinkler system pump. There are currently about 40 workers per day on the building site, taking advantage of the long, cool summer days we're having. | ||
![]() |
|
|
![]() |
![]() |
|
|
Putney Home
|
|
Admission
|
|
Planet Putney
|